Wheeled tractors are replacing crawler tractors because________________?
Show answer
Answer:
Consider the following statements?
In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having________________?
Show answer
Answer:
least cost slope
The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted, and pneumatic tyremounted machines would be respectively_________________?
Show answer
Answer:
75 and 83
Batching refers to________________?
Show answer
Answer:
controlling the quantity of each material into each batch
For excavating utility trenches with precise control of depth, the excavation equipment used is_______________?
Show answer
Answer:
Hoe
Which one of the following is not an excavating and moving type of equipment ?
Show answer
Answer:
Dump truck
The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is________________?
Show answer
Answer:
5515 kg
The correct sequence of these operations in tunnel construction is______________?
Show answer
Answer:
1,2,3,4,5
PERT is preferred for planning because of________________?
Show answer
Answer:
Consider the following features/factors
In resources levelling________________?
Show answer
Answer:
uniform demand of resources is achieved
Sinking fund is_______________?
Show answer
Answer:
the fund for rebuilding a structure when its economic life is over
During the construction period, price variation clause in contracts caters to__________________?
Show answer
Answer:
variation in cost in materials element, labour element and petrol-oil-lubricant element
The time corresponding to minimum total project cost is_______________?
Show answer
Answer:
between normal time and crash time
In the critical path method of construction planning, Free Float can be_____________?
Show answer
Answer:
2 and 3 are correct
A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be________________?
Show answer
Answer:
4.23 years
If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is________________?
Show answer
Answer:
16 days
The probability of completion of any activity within its expected time is_________________?
Show answer
Answer:
50%
An earth moving equipment costs Rs. 5,00,000/- and has an estimated life of 10 years and a salvage value of Rs. 50,000/-.What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069 ?
Show answer
Answer:
Rs. 31050
A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is: Drive wheels : 25000 kg Scraper wheels : 10000 kg If the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is_______________?
Show answer
Answer:
12500 kg
If the gross vehicle weight of a truck is 30 t and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is__________________?
Show answer
Answer:
900 kg
‹ Previous
1
2
3
4
5
Next ›
Home
Practice
Tests
Browse
Sign in
You are offline. Your answers are kept on this device and will sync when you are back online.
Install PakMCQ App
Practice faster with offline access!
Install
×
×
Install PakMCQ
Add to your iPhone / iPad Home Screen
1
Tap the
Share
button
at the bottom of Safari
2
Scroll down and select
Add to Home Screen
3
Tap
Add
in the top-right corner