Accounts Officer (2011) PPSC
Prime cost is the sum of
Explanation
Prime cost is the total of all direct costs: direct materials, direct labour, and other direct expenses (e.g. royalties on production). It excludes factory overheads — adding overheads to prime cost gives total factory (works) cost.
Related facts:
Prime cost + factory overhead = factory cost.
FOH (factory overhead) includes indirect materials and indirect labour.
Any option containing FOH is a distractor here.
Exam tip: "Prime" = primary, direct costs only. Any option containing FOH is wrong.