Skip to content
Sign in
Accounts Officer (2011) PPSC

Prime cost is the sum of

Tap an option to check the answer. You can also press A–D.

Explanation
Prime cost is the total of all direct costs: direct materials, direct labour, and other direct expenses (e.g. royalties on production). It excludes factory overheads — adding overheads to prime cost gives total factory (works) cost. Related facts: Prime cost + factory overhead = factory cost. FOH (factory overhead) includes indirect materials and indirect labour. Any option containing FOH is a distractor here. Exam tip: "Prime" = primary, direct costs only. Any option containing FOH is wrong.