Civil Engineering Share Crash project duration is obtained by summing the________________? A normal durations for all the activities Option A B crash durations for all activities Option B C crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Option C D crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Option D Tap an option to check the answer. You can also press A–D. No explanation yet. Suggest one Bookmark Report an error Share